Examples(Set 2) - Time and Work
6. men and women can complete a work in days. men and 60 women can complete a work in 3 days. men and women can do the same work in:
A. 10 days
B. 12 days
C. 8 days
D. 2 days
Explanation:
7. P can do a work in the same time in which Q and R together can do it. If P and Q work together, the work can be completed in 10days. R alone needs 50 days to complete the same work. then Q alone can do it in:
A. 30 days
B. 20 days
C. 25 days
D. 15 days
Explanation:
Amount of work P can do in 1 day = 1/ P
Amount of work Q can do in 1 day = 1/Q
Amount of work R, can do in 1 day = 1/ 50
Amount of work P and Q can do in 1 day
= 1/P+1/Q =1/10
given: 1/P=1/Q+1/50 (P can do a work in the same time in which Q and R together can do it)
solving both equations
1/Q=1/25
Q=25 days
8.A can do a piece of work in
6
hours. A and C together can do it in just
3
hours, while B and C together need
2
hours to finish the same work. B alone can complete the work in:
A.
6
hours
B.
3
hours
C.
5
hours
D.
2
hours
Explanation:
Amount of work A can do in 1 hour
1/A= 1/6
Amount of work A and C can do together in 1 hour
1/A+1/C= 1/3
Amount of work B and C can do together in 1 hour
1/B+1/C= 1/2
solving above equations
1/B=1/3
B=3
B alone will take 3 hours
9.A completes
80
%
of a work in
20
days. Then B also joins and A and B together finish the remaining work in
3
days. How long does it need for B if he alone completes the work?
A.
31
days
B.
22
days
C.
26
days
D.
37 and
1
2
days
Explanation:
Work done by A in 20 days
= 80/ 100
= 4/ 5
Work done by A in 1 day
= ( 4/ 5 )/ 20
= 1/ 25
Work done by A and B in 3 days
= 20/ 100
= 1/ 5 (because remaining 20 % is done in 3 days by A and B)
Work done by A and B in 1 day = (1/ 5)/3
=1/15
Work done by B in 1 day
= 1/ 15 − 1/ 25 = 2/ 75
Therefore, B can complete the work in 75/ 2 days
= 37 and 1/ 2 days
10.Machine P can print one lakh books in
8
hours. Machine Q can print the same number of books in
10
hours while machine R can print the same in
12
hours. All the machines started printing at
9
a.m. Machine P is stopped at
11
a.m. and the remaining two machines complete work. Approximately at what time will the printing of one lakh books be completed?
A.
11
a.m.
B.
3
p.m.
C.
1
p.m.
D.
2
p.m.
Explanation: Work done by P in 1hour =1/8
Work done by Q in 1hour = 1/10
Work done by R in 1hour =1/12
P worked for 2 hrs = 2*1/8
suppose Q and R worked for 'x' hrs then,
2*1/8+(1/10)*x+(1/12)x = 1
x=4.09
9+4.09 = 1pm